Letting Schedule for Brownwood District (FY 2014)
Brownwood District (FY 2014) |
Comanche | Eastland | Lampasas | Llano | Mills | San Saba | ||||||
Comanche County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
---|---|---|---|---|---|---|
0079-02-048 | US 67 | Actual | NOV 2013 | $4,490,030 | 1 | SEAL COAT |
0923-17-065 | CR | Actual | JUN 2014 | $684,062 | 6 | REPLACE BRIDGE AND APPROACHES |
Eastland County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0007-06-086 | IH 20 | Actual | DEC 2013 | $2,844,514 | 1 | RECONSTRUCT CENTER CONCRETE TRAFFIC BARRIER, LIGHTING, |
0257-04-025 | SH 6 | Actual | JUL 2014 | $5,495,042 | 1 | BASE OVERLAY AND 2 COURSE SURFACE TREATMENT |
0923-09-052 | CR | Actual | JAN 2014 | $713,911 | 6 | REPLACE BRIDGE AND APPROACHES |
0923-09-061 | CS | Actual | APR 2014 | $735,242 | 6 | REPLACE BRIDGE AND APPROACHES |
1697-02-019 | FM 2214 | Actual | MAY 2014 | $5,299,578 | 1 | REGRADE AND WIDEN EXISTING ROADWAY, FLEX BASE AND SURFACE |
2638-01-016 | SH 206 | Actual | JUL 2014 | $2,742,123 | 1 | BASE OVERLAY AND SEAL COAT |
Lampasas County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
2199-01-013 | FM 2313 | Actual | AUG 2014 | $38,752 | 10 | RAILROAD REPLANKING |
Llano County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0577-04-021 | SH 71 | Actual | MAR 2014 | $566,991 | 8 | TEXTURIZE SHOULDERS - PROFILE MARKERS |
Mills County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0923-23-025 | CR | Actual | NOV 2013 | $1,045,172 | 6 | REHAB STRUCTURE |
0923-23-027 | CR | Actual | APR 2014 | $601,294 | 6 | REPLACE BRIDGE AND APPROACHES |
1029-03-016 | FM 573 | Actual | AUG 2014 | $55,360 | 10 | RAILROAD REPLANKING |
San Saba County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0923-25-022 | PW | Actual | FEB 2014 | $874,683 | 10 | SCARIFY AND RESHAPE BASE COURSE AND PAVE ENTRANCE ROAD |
|