Monthly Local Let Maintenance Report For Dallas District As Of Jan 11, 2017 Page 1 Of 5

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyELLIS
HighwayIH0045
FromVARIOUS ROADWAYS IN THE ELLIS
ToCOUNTY MAINTENANCE SECTION
CSJ6201-06-001
Proj IDRMC - 620106001
Work TypeREFLECTORIZED PAVEMENT MARKINGS
 
0.001191208.00162028.5784.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-18-11
Work Began05-18-11
Work Completed
Time Computed07-17-11
Contract Working Days730
Addl Days Granted80
Working Days Charged810
Percent Time Used100
Contractor(s)
INTERSTATE ROAD MANAGEMENT CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6201-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04111801
Totals191208.000.00162028.5784.7

CountyKAUFMAN
HighwayMR0682
FromVARIOUS LOCATIONS AT THE
ToTERRELL STATE HOSPITAL
CSJ6207-65-001
Proj IDRMC - 620765001
Work TypeREHABILITATE ROADWAYS
 
0.001179519.150.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days25
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6207-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07101802
Totals179519.150.000.000.0

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6208-46-001
Proj IDRMC - 620846001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
88.77750652.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days107
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRAXTON TRANSPORTATION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6208-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09101801
Totals50652.700.000.000.0

CountyROCKWALL
HighwayIH0030
FromIH30 AT PARKER CREEK, PARKER CREEK
ToBRANCH, FM551 HACKBERRY CREEK, US175
CSJ6259-42-001
Proj IDBPM - 625942001
Work TypeREPLACE WINGWALLS & REPAIR SPALLING
 
0.001130385.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11131801
Totals130385.000.000.000.0

CountyDENTON
HighwayIH0035
FromVARIOUS ROADWAYS IN THE DENTON
ToCOUNTY MAINTENANCE SECTION
CSJ6268-51-001
Proj IDRMC - 626851001
Work TypeREFLECTORIZED PAVEMENT MARKERS
 
0.100223625.00113037.3550.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-08-15
Work Began05-08-15
Work Completed
Time Computed05-15-15
Contract Working Days730
Addl Days Granted0
Working Days Charged593
Percent Time Used81
Contractor(s)
M & M STRIPING & POWER WASHING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6268-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05141803
Totals223625.000.00113037.3550.5

CountyCOLLIN
HighwaySH0078
FromAT PRICE CREEK
ToIN COLLIN COUNTY
CSJ6274-02-001
Proj IDBPM - 627402001
Work TypeREPAIR OF ABUTMENT SLOPES
 
0.00149292.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days18
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MHB CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11141803
Totals49292.000.000.000.0

CountyDENTON
HighwayUS0380
FromVARIOUS ROADWAYS IN THE DENTON
ToCOUNTY MAINTENANCE SECTION
CSJ6276-59-001
Proj IDRMC - 627659001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.001325986.80165998.9250.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-14-15
Work Began09-14-15
Work Completed
Time Computed09-21-15
Contract Working Days365
Addl Days Granted365
Working Days Charged464
Percent Time Used63
Contractor(s)
ALTUS TRAFFIC MANAGEMENT LLC
SUBCONTRACTOR(S) FOR CCSJ: 6276-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03151802
Totals325986.800.00165998.9250.9

CountyDENTON
HighwayFM0455
FromFM, BI, AND BU ROADWAYS IN THE DENTON
ToCOUNTY MAINTENANCE SECTION
CSJ6277-57-001
Proj IDRMC - 627757001
Work TypeROADSIDE MOWING
 
0.001208017.00204073.0098.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-25-16
Work Began05-06-15
Work Completed
Time Computed11-01-16
Contract Working Days63
Addl Days Granted0
Working Days Charged27
Percent Time Used42
Contractor(s)
ANTHONY SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6277-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01151805
Totals208017.000.00204073.0098.1

CountyDENTON
HighwayIH0035E
FromDENTON COUNTY AREA OFFICE
ToAND MAINTENANCE FACILITIES
CSJ6278-25-001
Proj IDSUP - 627825001
Work TypeJANITORIAL AND GROUNDS MAINTENANCE
 
0.00174418.5874465.4299.9
Work Order12-17-14
Work Began01-01-15
Work Completed
Time Computed01-01-15
Contract Working Days731
Addl Days Granted90
Working Days Charged728
Percent Time Used88
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6278-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01151830
Totals74418.582348.7974465.4299.9

CountyCOLLIN
HighwayUS0075
FromVARIOUS LOCATIONS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6283-24-001
Proj IDRMC - 628324001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
0.001274893.80175901.5763.9
Work Order08-27-15
Work Began09-01-15
Work Completed
Time Computed09-08-15
Contract Working Days730
Addl Days Granted0
Working Days Charged477
Percent Time Used65
Contractor(s)
GHB EQUIPMENT COMPANY, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6283-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06151801
Totals274893.801384.30175901.5763.9

CountyDALLAS
HighwayIH0030
FromIH 30 AT ST PAUL UNDERPASS IN THE
ToNORTHEAST DALLAS MAINTENANCE SECTION
CSJ6286-56-001
Proj IDRMC - 628656001
Work TypeINSTALL FENCE
 
0.001102710.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days10
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07151804
Totals102710.000.000.000.0

CountyCOLLIN
HighwaySH0078
FromCOLLIN
ToCOUNTY
CSJ6288-30-001
Proj IDSUP - 628830001
Work TypePICNIC AREA AND LANDSCAPE
 
0.00188682.2851591.1458.1
Work Order07-22-15
Work Began08-01-15
Work Completed
Time Computed08-01-15
Contract Working Days731
Addl Days Granted0
Working Days Charged516
Percent Time Used70
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6288-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08151830
Totals88682.281875.0051591.1458.1

CountyCOLLIN
HighwaySH0005
FromCOLLIN COUNTY AREA OFFICE AND
ToMAINTENANCE FACILITY
CSJ6288-31-001
Proj IDSUP - 628831001
Work TypeJANITORIAL MAINTENANCE
 
0.00139490.6426003.3765.8
Work Order07-29-15
Work Began08-01-15
Work Completed
Time Computed08-01-15
Contract Working Days731
Addl Days Granted0
Working Days Charged515
Percent Time Used70
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6288-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08151834
Totals39490.641529.6126003.3765.8

CountyDENTON
HighwayFM0407
FromVARIOUS ROADWAYS IN THE DENTON
ToCOUNTY MAINTENANCE SECTION
CSJ6288-37-001
Proj IDSUP - 628837001
Work TypeLITTER REMOVAL
 
0.001182875.64116566.1763.7
Work Order08-06-15
Work Began09-01-15
Work Completed
Time Computed09-01-15
Contract Working Days731
Addl Days Granted0
Working Days Charged485
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6288-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09151831
Totals182875.6410494.23116566.1763.7

CountyROCKWALL
HighwayIH0030
FromIH, US, SH AND FM ROADWAYS IN
ToROCKWALL & COLLIN COUNTY
CSJ6289-97-001
Proj IDRMC - 628997001
Work TypeVEGETATION MANAGEMENT
 
0.001261360.00101501.0038.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-21-16
Work Began03-31-16
Work Completed
Time Computed11-21-16
Contract Working Days50
Addl Days Granted0
Working Days Charged39
Percent Time Used78
Contractor(s)
GANT CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6289-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151801
Totals261360.000.00101501.0038.8

CountyKAUFMAN
HighwayIH0020
FromVARIOUS LOCATION IN THE KAUFMAN/
ToROCKWALL MAINTENANCE SECTION
CSJ6291-42-001
Proj IDRMC - 629142001
Work TypeRAISED PAVEMENT MARKERS
 
0.001133279.701311.000.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-01-16
Work Began00-00-00
Work Completed
Time Computed12-08-16
Contract Working Days730
Addl Days Granted0
Working Days Charged15
Percent Time Used2
Contractor(s)
TEXAS TMA RENTAL
SUBCONTRACTOR(S) FOR CCSJ: 6291-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03161801
Totals133279.700.001311.000.9

CountyCOLLIN
HighwaySH0005
FromCOLLIN COUNTY AREA OFFICE AND
ToMAINTENANCE FACILITY
CSJ6291-67-001
Proj IDSUP - 629167001
Work TypeGROUNDS MAINTENANCE
 
0.00118000.006000.0033.3
Work Order07-29-15
Work Began08-01-15
Work Completed
Time Computed08-01-15
Contract Working Days731
Addl Days Granted0
Working Days Charged515
Percent Time Used70
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6291-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08151833
Totals18000.000.006000.0033.3

CountyDENTON
HighwayBS0114K
FromVARIOUS ROADWAYS IN THE DENTON
ToCOUNTY MAINTENANCE SECTION
CSJ6291-92-001
Proj IDRMC - 629192001
Work TypeTREE TRIMMING & TREE AND BRUSH
 
0.10094032.7949940.4853.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-31-16
Work Began04-06-16
Work Completed
Time Computed04-07-16
Contract Working Days365
Addl Days Granted0
Working Days Charged266
Percent Time Used72
Contractor(s)
DRC EMERGENCY SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6291-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151804
Totals94032.790.0049940.4853.1

CountyDALLAS
HighwayIH0045
FromHUTCHINS TXDOT OFFICE
ToMAINTENANCE FACILITIES
CSJ6292-52-001
Proj IDSUP - 629252001
Work TypeJANITORIAL MAINTENANCE
 
0.00126700.0012000.0044.9
Work Order08-06-15
Work Began09-01-15
Work Completed
Time Computed09-01-15
Contract Working Days731
Addl Days Granted0
Working Days Charged487
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09151835
Totals26700.00750.0012000.0044.9

CountyKAUFMAN
HighwaySH0034
FromKAUFMAN TXDOT
ToFACILITY
CSJ6292-54-001
Proj IDSUP - 629254001
Work TypeJANITORIAL MAINTENANCE
 
0.00136950.0020805.0056.3
Work Order08-19-15
Work Began09-01-15
Work Completed
Time Computed09-01-15
Contract Working Days731
Addl Days Granted0
Working Days Charged483
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09151837
Totals36950.001400.0020805.0056.3

page 1 | page 2 | page 3 | page 4 | page 5