Monthly State Let Construction Report For Lufkin District As Of Jan 11, 2016 Page 1 Of 4

Last Update: Tuesday, January 12, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountySHELBY
Highway SH 7
From SAN AUGUSTINE COUNTY LINE
To 4.429 MI N OF FM 2913
CSJ 0059-03-018
Proj ID STP 2014(851)HES
Work Type IMPROVE GUARDRAIL TO DES STANDARDS
 
16.929 839398.00 0.00 845709.10 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-29-14
Work Began 08-18-14
Work Completed 02-10-15
Time Computed 08-14-14
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 47
Percent Time Used 120
Contractor(s)
ODUM SERVICES, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0059-03-018
L.C. JORDAN & SON( 55.77%)
Contract # 06143047
Totals 839398.00 0.00 845709.10 100.0

CountySHELBY
Highway SH 7
From 4.432 MI E OF FM 2913
To US 96
CSJ 0059-04-045
Proj ID STP 2016(419)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
9.550 1260125.90 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 123
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0059-04-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153026
Totals 1260125.90 0.00 0.00 0.0

CountySHELBY
Highway US 96
From 1.46 MI N OF SH 87 IN CENTER
To SH 87 IN CENTER
CSJ 0063-06-096
Proj ID NH 2016(271)
Work Type PLANE EXISTING SURFACE AND OVERLAY
 
3.275 2189250.49 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 53
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0063-06-096
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11153027
Totals 2189250.49 0.00 0.00 0.0

CountySAN AUGUSTINE
Highway SH 21 ETC
From SH 147
To FM 1
CSJ 0064-04-037
Proj ID STP 2016(274)
Work Type RESURFACE WITH SEAL COAT
 
177.815 7619981.14 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 63
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0064-04-037
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153225
Totals 7619981.14 0.00 0.00 0.0

CountySAN AUGUSTINE
Highway SH 21
From SH 147
To FM 1
CSJ 0064-04-038
Proj ID STP 2016(120)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
15.567 1848256.10 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-21-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 176
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0064-04-038
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10153002
Totals 1848256.10 0.00 0.00 0.0

CountySABINE
Highway US 96
From FM 1
To JASPER COUNTY LINE
CSJ 0064-06-052
Proj ID NH 2015(418)
Work Type RESURFACE WITH MICROSURFACING
 
29.170 1880399.04 0.00 1884304.49 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-13-15
Work Began 04-20-15
Work Completed 09-16-15
Time Computed 04-20-15
Contract Working Days 34
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 88
Contractor(s)
NY-MAC ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0064-06-052
PANOLA SIGN & BARRICADE, INC.(0.87%)
CRABTREE BARRICADE SYSTEMS, INC. (7.96%)
Contract # 12143022
Totals 1880399.04 0.00 1884304.49 100.0

CountySABINE
Highway FM 1
From SH 184
To 6.1 MI S OF SH 184
CSJ 0064-11-013
Proj ID STP 2014(737)HRR
Work Type SAFETY TREAT FIXED OBJECTS
 
21.014 1186968.00 0.00 1144892.32 96.4
Work Order 07-22-14
Work Began 08-11-14
Work Completed  
Time Computed 08-07-14
Contract Working Days 205
Addl Days Granted 0
Working Days Charged 181
Percent Time Used 88
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0064-11-013
PANOLA SIGN & BARRICADE, INC.(0.89%)
DUSTIN ALLEN, INC. ( 10.08%)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.19%)
LUDCO, INC.(1.48%)
Contract # 06143037
Totals 1186968.00 0.00 1144892.32 96.4

CountySABINE
Highway FM 1
From SH 184
To SS 1
CSJ 0064-11-014
Proj ID STP 1502(459)HES
Work Type PROVIDE ADDITIONAL PAVED SURF WIDTH
 
6.038 3634869.32 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-09-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 104
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0064-11-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153245
Totals 3634869.32 0.00 0.00 0.0

CountyHOUSTON
Highway US 287
From 2.1 MI N OF FM 2663
To 0.761 MI S OF SL 304
CSJ 0109-04-029
Proj ID STP 2016(483)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
14.264 1611863.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 145
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0109-04-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163028
Totals 1611863.00 0.00 0.00 0.0

CountyTRINITY
Highway SH 19 ETC
From HOUSTON COUNTY LINE
To SH 94 IN TRINITY
CSJ 0109-07-050
Proj ID STP 2015(321)
Work Type RESURFACE WITH SEAL COAT
 
208.759 8618179.28 0.00 8177164.77 95.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-10-15
Work Began 02-28-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 65
Addl Days Granted 0
Working Days Charged 83
Percent Time Used 127
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0109-07-050
INTERSTATE BARRICADES & MARKINGS, INC. ( 14.05%)
Contract # 11143003
Totals 8618179.28 0.00 8177164.77 95.1

CountyHOUSTON
Highway SH 21
From FM 1280
To 2.32 MI E OF FM 2967
CSJ 0117-06-044
Proj ID NH 1502(067)
Work Type RECONSTRUCT AND ADD PASSING LANES
 
7.337 11812489.64 309496.69 1743886.77 14.7
Work Order 06-01-15
Work Began 09-02-15
Work Completed  
Time Computed 07-02-15
Contract Working Days 314
Addl Days Granted 0
Working Days Charged 67
Percent Time Used 21
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0117-06-044
AMERICAN REMEDIATION OPTIONS, INC. (3.78%)
BIG CREEK CONSTRUCTION, LTD. ( 18.95%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.95%)
J & M CONTRACTING, COMPANY ( 22.49%)
PANOLA SIGN & BARRICADE, INC.(0.31%)
WEST TEXAS RUMBLE STRIP(0.06%)
Contract # 04153055
Totals 11812489.64 309496.69 1743886.77 14.7

CountyHOUSTON
Highway SH 21
From 2.32 MI E OF FM 2967
To SH 7
CSJ 0117-07-040
Proj ID NH 1502(460)
Work Type RECONST PVMNT & ADD PASSING LANES
 
5.724 11462865.25 0.00 1384210.00 12.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-06-15
Work Began 11-10-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 408
Addl Days Granted 0
Working Days Charged 24
Percent Time Used 5
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0117-07-040
DREWERY BROS TREE SERVICE, INC.(0.49%)
DUSTY ALLEN, INC.(0.56%)
J&M CONTRACTING COMPANY(8.44%)
PANOLA SIGN & BARRICADE, INC.(0.34%)
TEXOP CONSTRUCTION (0.95%)
WEST TEXAS RUMBLE STRIP(0.06%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.39%)
Contract # 07153209
Totals 11462865.25 0.00 1384210.00 12.0

CountyNACOGDOCHES
Highway SH 21
From 0.40 MI W OF FM 226
To FM 3276
CSJ 0118-08-060
Proj ID C 118-8-60
Work Type GRADING, STRUT, BASE, HMAC SURFACE
 
4.231 7883681.86 84375.00 7666464.69 98.8
Work Order 10-03-12
Work Began 01-11-13
Work Completed  
Time Computed 11-01-12
Contract Working Days 235
Addl Days Granted 79
Working Days Charged 429
Percent Time Used 136
Contractor(s)
FEDERAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0118-08-060
N-LINE TRAFFIC MAINTENANCE, L.P. (0.17%)
AMERICAN REMEDIATION OPTIONS, INC. (1.62%)
VERITAS SUPPLY, INC. (1.03%)
DREWERY CONSTRUCTION COMPANY, INCORPORATED ( 32.69%)
DUSTROL, INC.(0.42%)
TEXAS STAR TRANSPORT, LP (1.74%)
STRIPING TECHNOLOGY, L.P.(0.76%)
O DIRT (1.25%)
Contract # 07123023
Totals 7883681.86 84375.00 7666464.69 98.8

CountySAN AUGUSTINE
Highway SH 21
From AT US 96
To .
CSJ 0118-10-055
Proj ID STP 2015(154)
Work Type INTERSECTION IMPROVEMENTS
 
0.300 3381562.15 6750.62 3310202.49 97.8
Work Order 11-06-14
Work Began 03-16-15
Work Completed  
Time Computed 11-22-14
Contract Working Days 90
Addl Days Granted 36
Working Days Charged 124
Percent Time Used 98
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0118-10-055
A R BROTHERS CONSTRUCTION SERVICES, INC. (9.78%)
PANOLA SIGN & BARRICADE, INC.(0.30%)
STRIPING TECHNOLOGY, L.P.(1.07%)
DREWERY & WHEATON, LLC (1.60%)
SOUTH TEXAS ILLUMINATION, LLC(4.34%)
FREDONIA CONSTRUCTION SERVICES (0.27%)
ADCOCK 4 INVESTMENTS, LLC(4.72%)
AMERICAN REMEDIATION OPTIONS, INC. (0.29%)
Contract # 09143230
Totals 3381562.15 6750.62 3310202.49 97.8

CountySAN AUGUSTINE
Highway SH 21
From AT PERKINS CREEK
To .
CSJ 0118-10-058
Proj ID BR 2016(484)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.058 5229087.95 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 263
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0118-10-058
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163207
Totals 5229087.95 0.00 0.00 0.0

CountySHELBY
Highway US 84
From RUSK COUNTY LINE
To US 59 IN TIMPSON
CSJ 0123-07-018
Proj ID STP 2013(516)
Work Type RECONSTRUCT PAVEMENT
 
6.413 5459220.41 0.00 5264803.42 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-25-14
Work Began 05-12-14
Work Completed 06-24-15
Time Computed 05-11-14
Contract Working Days 157
Addl Days Granted 0
Working Days Charged 155
Percent Time Used 98
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0123-07-018
ACU CONSTRUCTION LLC (0.40%)
A.J.J.A . TRUCKING, INC. (1.00%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.42%)
DREWERY"S TREE SERVICE AND CONSTRUCTION CO., INC.(0.27%)
DREWERY & WHEATON, LLC (0.11%)
J & M CONTRACTING, COMPANY (1.90%)
MURRAY CONSTRUCTION(0.45%)
ODUM SERVICES, L.P.(0.89%)
PANOLA SIGN & BARRICADE, INC.(0.38%)
STRIPING TECHNOLOGY, L.P.(1.39%)
COWBELL TRAFFIC SERVICE, INC.(0.19%)
FREDONIA CONSTRUCTION SERVICES (0.16%)
Contract # 02143027
Totals 5459220.41 0.00 5264803.42 100.0

CountySHELBY
Highway FM 415
From AT BEAR BAYOU
To .
CSJ 0123-08-010
Proj ID BR 1502(621)
Work Type BRIDGE REPLACEMENT
 
0.165 1352960.21 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-30-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 119
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0123-08-010
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153242
Totals 1352960.21 0.00 0.00 0.0

CountySHELBY
Highway US 84
From AT SABINE RIVER
To .
CSJ 0175-01-005
Proj ID BR 2005(5)
Work Type REPLACE BRIDGE
 
0.209 9916183.38 179406.57 5674636.88 57.2
CountySHELBY
Highway US 84
From 0.62 MI W OF SABINE RIVER
To SABINE RIVER BRIDGE
CSJ 0175-02-078
Proj ID BR 1302(051)
Work Type GRADING, STRUCTURE, BASE, SURFACING
 
0.479 4226063.48 13990.00 2161658.50 51.1
CountySHELBY
Highway VA
From SABINE RIVER BRIDGE
To 0.1 MI E OF LOUISIANA 5
CSJ 0911-39-022
Proj ID CC 911-39-22
Work Type GRADING, STRUCTURE, BASE, SURFACING
 
0.543 6269852.76 44502.35 4707606.21 75.0
Work Order 09-26-13
Work Began 01-06-14
Work Completed  
Time Computed 12-27-13
Contract Working Days 611
Addl Days Granted 0
Working Days Charged 501
Percent Time Used 81
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0175-01-005
SOUTHWEST ENVIRONMENT SERVICES LLC (2.06%)
DUSTROL, INC.(0.34%)
FBL & ASSOCIATES (0.67%)
HOUSTON SAWING & DRILLING(0.04%)
MOORE BROTHERS CONSTRUCTION COMPANY( 12.37%)
RDI FOUNDATION DRILLING(7.41%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.84%)
W.O.E. CONSTRUCTION(0.28%)
HIGHWAY 19 CONSTRUCTION, LLC (6.48%)
STRIPING TECHNOLOGY, L.P.(0.71%)
RICE ENVIRONMENTAL SERVICES(0.09%)
BRUMLEY DEVELOPMENT, LLC (0.00%)
MCL CONTRACTING, LLC (0.39%)
MILLER TRANSPORTATION(0.00%)
DAVID LAWLER CONSTRUCTION(0.07%)
LFI FT PIERCE, INC (0.04%)
ODUM SERVICES, L.P.(0.23%)
PROTECTION SERVICES INC. (0.03%)
DYKON BLASTING CORP(0.54%)
Contract # 07133206
Totals 20412099.62 237898.92 12543901.59 61.4

CountyNACOGDOCHES
Highway US 59
From 0.24 MI S OF FM 95 W
To US 259
CSJ 0175-07-056
Proj ID NH 2014(686)
Work Type MILL & INLAY SECTIONS AND SEAL
 
13.421 3335178.93 0.00 3536813.39 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-20-14
Work Began 07-28-14
Work Completed 09-14-15
Time Computed 06-05-14
Contract Working Days 39
Addl Days Granted 14
Working Days Charged 70
Percent Time Used 132
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0175-07-056
ACU CONSTRUCTION LLC (3.02%)
PANOLA SIGN & BARRICADE, INC.(0.14%)
STRIPING TECHNOLOGY, L.P.(4.11%)
PINTO CONSTRUCTION CO., INC. (9.99%)
FREDONIA CONSTRUCTION SERVICES (0.27%)
Contract # 04143219
Totals 3335178.93 0.00 3536813.39 100.0

CountyNACOGDOCHES
Highway US 59
From 2.59 MI S OF RUSK COUNTY LINE
To US 259
CSJ 0175-07-057
Proj ID STP 2016(420)HES
Work Type IMPROVE GUARDRAIL TO DES STANDARDS
 
22.534 295401.65 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 36
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
3LW MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0175-07-057
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153023
Totals 295401.65 0.00 0.00 0.0

page 1 | page 2 | page 3 | page 4