Monthly State Let Construction Report For Lufkin District As Of Feb 10, 2017 Page 1 Of 4

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyNACOGDOCHES ETC
HighwaySH 7 ETC
FromSL 224
ToFM 2713
CSJ0059-01-060
Proj IDSTP 2017(249)
Work TypeRESURFACE WITH SEAL COAT
 
224.67411201892.340.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-04-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days91
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0059-01-060
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11163025
Totals11201892.340.000.000.0

CountySHELBY
HighwaySH 7
From4.432 MI E OF FM 2913
ToUS 96
CSJ0059-04-045
Proj IDSTP 2016(419)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
9.5501260125.90878157.9869.8
Work Order03-31-16
Work Began05-23-16
Work Completed
Time Computed05-02-16
Contract Working Days123
Addl Days Granted0
Working Days Charged126
Percent Time Used102
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0059-04-045
ODUM SERVICES, L.P. (14.14)
Contract #12153026
Totals1260125.9055518.68878157.9869.8

CountySHELBY
HighwayUS 96
From1.46 MI N OF SH 87 IN CENTER
ToSH 87 IN CENTER
CSJ0063-06-096
Proj IDNH 2016(271)
Work TypePLANE EXISTING SURFACE AND OVERLAY
 
3.2752189250.492186665.0999.8
Work Order02-22-16
Work Began02-29-16
Work Completed
Time Computed02-24-16
Contract Working Days53
Addl Days Granted0
Working Days Charged46
Percent Time Used86
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0063-06-096
DUSTROL, INC. (7.29)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC (12.57)
PANOLA SIGN & BARRICADE, INC. (0.33)
STRIPING TECHNOLOGY, L.P. (3.10)
W.O.E. CONSTRUCTION (0.16)
STRIPING SYSTEMS, INC. (0.06)
Contract #11153027
Totals2189250.490.002186665.0999.8

CountySAN AUGUSTINE
HighwaySH 21
FromSH 147
ToFM 1
CSJ0064-04-038
Proj IDSTP 2016(120)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
15.5671848256.101645524.3689.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-21-15
Work Began01-18-16
Work Completed
Time Computed00-00-00
Contract Working Days176
Addl Days Granted0
Working Days Charged187
Percent Time Used106
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0064-04-038
AMERICAN REMEDIATION OPTIONS, INC. (26.79)
Contract #10153002
Totals1848256.100.001645524.3689.4

CountySABINE
HighwayFM 1
FromSH 184
ToSS 1
CSJ0064-11-014
Proj IDSTP 1502(459)HES
Work TypePROVIDE ADDITIONAL PAVED SURF WIDTH
 
6.0383634869.323353701.5792.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-09-15
Work Began05-03-16
Work Completed
Time Computed00-00-00
Contract Working Days104
Addl Days Granted40
Working Days Charged109
Percent Time Used75
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0064-11-014
AMERICAN REMEDIATION OPTIONS, INC. (3.63)
CRABTREE BARRICADE SYSTEMS, INC. (1.61)
MOORE BROTHERS CONSTRUCTION COMPANY (5.31)
PANOLA SIGN & BARRICADE, INC. (0.52)
A R BROTHERS CONSTRUCTION SERVICES, INC. (2.22)
Contract #07153245
Totals3634869.320.003353701.5792.2

CountyHOUSTON
HighwayUS 287
From2.1 MI N OF FM 2663
To0.761 MI S OF SL 304
CSJ0109-04-029
Proj IDSTP 2016(483)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
14.2641611863.001637982.4299.9
Work Order03-29-16
Work Began05-09-16
Work Completed
Time Computed05-09-16
Contract Working Days145
Addl Days Granted7
Working Days Charged124
Percent Time Used81
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0109-04-029
AMERICAN REMEDIATION OPTIONS, INC. (6.57)
A R BROTHERS CONSTRUCTION SERVICES, INC. (55.22)
PANOLA SIGN & BARRICADE, INC. (0.87)
Contract #01163028
Totals1611863.0020002.101637982.4299.9

CountyHOUSTON
HighwaySH 19
FromSH 7
To1.616 MI N OF FM 231
CSJ0109-05-040
Proj IDSTP 2017(045)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
17.231921752.50345329.4937.4
Work Order11-08-16
Work Began12-12-16
Work Completed
Time Computed12-08-16
Contract Working Days140
Addl Days Granted0
Working Days Charged26
Percent Time Used18
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0109-05-040
ODUM SERVICES, L.P. (10.76)
Contract #09163218
Totals921752.5086142.58345329.4937.4

CountyHOUSTON
HighwaySH 21
FromFM 1280
To2.32 MI E OF FM 2967
CSJ0117-06-044
Proj IDNH 1502(067)
Work TypeRECONSTRUCT AND ADD PASSING LANES
 
7.33711812489.6410631968.4590.0
Work Order06-01-15
Work Began09-02-15
Work Completed
Time Computed07-02-15
Contract Working Days314
Addl Days Granted0
Working Days Charged279
Percent Time Used88
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0117-06-044
AMERICAN REMEDIATION OPTIONS, INC. (3.78)
BIG CREEK CONSTRUCTION, LTD. (18.95)
INTERSTATE BARRICADES & MARKINGS, INC. (0.95)
J & M CONTRACTING, COMPANY (22.49)
PANOLA SIGN & BARRICADE, INC. (0.31)
WEST TEXAS RUMBLE STRIP (0.06)
Contract #04153055
Totals11812489.64592684.0410631968.4590.0

CountyHOUSTON
HighwaySH 21
From2.32 MI E OF FM 2967
ToSH 7
CSJ0117-07-040
Proj IDNH 1502(460)
Work TypeRECONST PVMNT & ADD PASSING LANES
 
5.72411462865.255352785.4246.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-06-15
Work Began11-10-15
Work Completed
Time Computed00-00-00
Contract Working Days408
Addl Days Granted8
Working Days Charged207
Percent Time Used49
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0117-07-040
DREWERY BROS TREE SERVICE, INC. (0.49)
DUSTY ALLEN, INC. (0.56)
J&M CONTRACTING COMPANY (8.44)
PANOLA SIGN & BARRICADE, INC. (0.34)
TEXOP CONSTRUCTION (0.95)
WEST TEXAS RUMBLE STRIP (0.06)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.39)
FREDONIA CONSTRUCTION SERVICES (0.10)
BATTEN DRILLING, INC. (0.01)
STRIPING TECHNOLOGY, L.P. (0.90)
Contract #07153209
Totals11462865.250.005352785.4246.6

CountyHOUSTON
HighwaySH 21
From0.65 MI S OF SL 304
To2.567 MI S OF FM 1733
CSJ0118-01-019
Proj IDSTP 2017(307)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
25.3462981766.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days211
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0118-01-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173016
Totals2981766.600.000.000.0

CountySAN AUGUSTINE
HighwaySH 21
FromAT PERKINS CREEK
To.
CSJ0118-10-058
Proj IDBR 2016(484)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.0585229087.95552817.1710.5
Work Order03-08-16
Work Began00-00-00
Work Completed
Time Computed05-09-16
Contract Working Days263
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0118-10-058
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01163207
Totals5229087.95462097.17552817.1710.5

CountySABINE ETC
HighwaySH 21 ETC
FromSAN AUGUSTINE CO LINE
ToFM 330
CSJ0119-02-020
Proj IDSTP 1602(450)HES
Work TypeRUMBLE STRIPS
 
83.672684933.2483714.5612.2
Work Order09-20-16
Work Began11-07-16
Work Completed
Time Computed11-07-16
Contract Working Days23
Addl Days Granted14
Working Days Charged20
Percent Time Used54
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0119-02-020
COWBELL TRAFFIC SERVICES, INC. (2.25)
Contract #08163042
Totals684933.2414783.3583714.5612.2

CountySHELBY ETC
HighwayUS 84 ETC
FromRUSK COUNTY LINE
ToUS 59
CSJ0123-07-019
Proj IDSTP 2017(310)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
24.2951254729.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days211
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0123-07-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173026
Totals1254729.100.000.000.0

CountySHELBY
HighwayFM 415
FromAT BEAR BAYOU
To.
CSJ0123-08-010
Proj IDBR 1502(621)
Work TypeBRIDGE REPLACEMENT
 
0.1651352960.21344375.3025.4
Work Order10-30-15
Work Began07-19-16
Work Completed
Time Computed03-01-16
Contract Working Days119
Addl Days Granted0
Working Days Charged24
Percent Time Used20
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0123-08-010
PANOLA SIGN & BARRICADE, INC. (0.71)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.75)
AMERICAN REMEDIATION OPTIONS, INC. (4.69)
STRIPING TECHNOLOGY, L.P. (1.22)
MCL CONTRACTING, LLC (0.21)
Contract #08153242
Totals1352960.2140403.95344375.3025.4

CountySHELBY
HighwayUS 84
FromAT SABINE RIVER
To.
CSJ0175-01-005
Proj IDBR 2005(5)
Work TypeREPLACE BRIDGE
 
0.2099916183.389557293.5696.3
CountySHELBY
HighwayUS 84
From0.62 MI W OF SABINE RIVER
ToSABINE RIVER BRIDGE
CSJ0175-02-078
Proj IDBR 1302(051)
Work TypeGRADING, STRUCTURE, BASE, SURFACING
 
0.4794226063.482927334.7369.2
CountySHELBY
HighwayVA
FromSABINE RIVER BRIDGE
To0.1 MI E OF LOUISIANA 5
CSJ0911-39-022
Proj IDCC 911-39-22
Work TypeGRADING, STRUCTURE, BASE, SURFACING
 
0.5436269852.765719392.5791.2
Work Order09-26-13
Work Began01-06-14
Work Completed
Time Computed12-27-13
Contract Working Days611
Addl Days Granted193
Working Days Charged759
Percent Time Used94
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0175-01-005
SOUTHWEST ENVIRONMENT SERVICES LLC (2.06)
DUSTROL, INC. (0.34)
FBL & ASSOCIATES (0.67)
HOUSTON SAWING & DRILLING (0.04)
MOORE BROTHERS CONSTRUCTION COMPANY (12.37)
RDI FOUNDATION DRILLING (7.41)
TOTAL HIGHWAY MAINTENANCE, LLC (0.84)
W.O.E. CONSTRUCTION (0.28)
HIGHWAY 19 CONSTRUCTION, LLC (6.48)
STRIPING TECHNOLOGY, L.P. (0.71)
RICE ENVIRONMENTAL SERVICES (0.09)
BRUMLEY DEVELOPMENT, LLC (0.00)
MCL CONTRACTING, LLC (0.39)
MILLER TRANSPORTATION (0.00)
DAVID LAWLER CONSTRUCTION (0.07)
LFI FT PIERCE, INC (0.04)
ODUM SERVICES, L.P. (0.23)
PROTECTION SERVICES INC. (0.03)
DYKON BLASTING CORP (0.54)
AGGREGATE TECHNOLOGIES, INC. (0.08)
VALLEY PLACERS, LLC (0.22)
JEFF WILSON BORING (0.01)
FRAMERS OF TENNESSEE, LLC (0.04)
Contract #07133206
Totals20412099.62549272.4518204020.8689.1

CountyNACOGDOCHES
HighwayBU 59-F
FromAT EAST COLLEGE IN NACOGDOCHES
To.
CSJ0175-08-044
Proj IDCC 175-8-44
Work TypeMODIFY EXISTING SIGNAL
 
0.01058317.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-31-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days15
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0175-08-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11163029
Totals58317.000.000.000.0

CountyNACOGDOCHES
HighwayUS 59
FromLP 224
To1.255 MI S OF LP 224
CSJ0176-01-094
Proj IDSTP 2014(918)HES
Work TypeINSTALL RAISED MEDIAN
 
1.67214030469.7211983479.6585.4
Work Order09-12-14
Work Began01-07-15
Work Completed
Time Computed01-05-15
Contract Working Days532
Addl Days Granted0
Working Days Charged506
Percent Time Used95
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0176-01-094
BRADCO, LLC (6.00)
DUSTIN ALLEN, INC. (0.64)
DUSTROL, INC. (1.29)
ECM ENVIRONMENTAL SERVICES, INC. (0.32)
MOORE BROTHERS CONSTRUCTION COMPANY (17.80)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.23)
PINTO CONSTRUCTION CO., INC. (7.29)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.41)
STRIPING TECHNOLOGY, L.P. (2.01)
TEXAS TRAFFIC CONTROL SYSTEMS, INC. (1.36)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.80)
STEEL EFFECTS (0.00)
L MOBLEY CONCRETE CONSTRUCTION (6.95)
CARTHAGE DRILLING, INC. (0.07)
BREDA COMPANY, INC. (0.49)
CPAVE, INC. (0.17)
PEREZ CONSTRUCTION CO. (0.35)
ADCOCK 4 INVESTMENTS, LLC, DBA BRADCO (5.91)
Contract #07143005
Totals14030469.721047796.8311983479.6585.4

CountyNACOGDOCHES
HighwayUS 59
FromGRASS MEDIAN S OF SL 224
ToANGELINA RIVER BRIDGE
CSJ0176-01-107
Proj IDNH 1602(177)
Work TypeOVERLAY WITH PFC
 
6.6321598523.471494424.6593.4
Work Order06-20-16
Work Began10-03-16
Work Completed
Time Computed08-22-16
Contract Working Days37
Addl Days Granted0
Working Days Charged19
Percent Time Used51
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0176-01-107
CLARK CONSTRUCTION OF TEXAS, INC. (18.90)
DIAMOND SURFACE, INC. (0.49)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.39)
STRIPING TECHNOLOGY, L.P. (2.77)
TEXAS ALTERNATIVE GRASSER, INC. (0.70)
Contract #05163032
Totals1598523.470.001494424.6593.4

CountyNACOGDOCHES ETC
HighwayUS 59 ETC
FromAT ANGELINA RIVER
To.
CSJ0176-01-109
Proj IDBR 2016(696)
Work TypeUPGRADE BRIDGE AND APPROACH RAILING
 
9.5882458818.052031506.2783.9
Work Order04-19-16
Work Began06-15-16
Work Completed
Time Computed05-19-16
Contract Working Days96
Addl Days Granted0
Working Days Charged139
Percent Time Used144
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0176-01-109
DUSTIN ALLEN, INC. (6.89)
J & M CONTRACTING, COMPANY (13.30)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.03)
STRIPING TECHNOLOGY, L.P. (0.74)
STRIPING SYSTEMS, INC. (0.06)
Contract #02163227
Totals2458818.05133227.852031506.2783.9

CountyANGELINA
HighwayUS 59
From.9 MILES N. OF LP 287 (N) (@ UP RR)
To.1 MILES N. OF LP 287 (N)
CSJ0176-02-090
Proj IDSTP 99(770)RGS
Work TypeREPLACE RAILROAD UNDERPASS
 
0.55413760249.9313000589.1294.6
CountyANGELINA
HighwayUS 59
From0.13 MI N OF FM 3439
ToLP 287/US 69
CSJ0176-02-105
Proj IDSTP 2012(501)HES
Work TypeCONSTRUCT INTERCHANGE
 
1.82938418975.2839255712.9699.9
Work Order08-20-12
Work Began09-10-12
Work Completed
Time Computed09-10-12
Contract Working Days764
Addl Days Granted104
Working Days Charged876
Percent Time Used100
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0176-02-090
HIGHWAY TECHNOLOGIES, INC. (0.12)
BATTERSON,LLP (0.57)
DUSTIN ALLEN, INC. (0.72)
A. H. BAKER SERVICES, INC. (10.54)
W. W. FOUNDATION DRILLING, LTD. (1.86)
MOORE BROTHERS CONSTRUCTION COMPANY (9.56)
DYWIDAG-SYSTEMS INTERNATIONAL_USA,INC. (0.07)
DUSTROL, INC. (0.02)
DRILL TECH DRILLING & SHORING, INC. (1.56)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.17)
RAILWORKS TRACK SYSTEMS, INC. (0.14)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.17)
A R BROTHERS CONSTRUCTION SERVICES, INC. (0.54)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC. (2.70)
ALLEN LOGGINGS & SONS, INC. (0.19)
FUGRO CONSULTANTS LP (0.07)
MESA ROD BUSTERS, INC. (0.80)
EROSION CONTROL, INC. (0.92)
EAST TEXAS LANDSCAPING, INC. (0.13)
TEX OP CONSTRUCTION, LP (0.42)
PINTO CONSTRUCTION CO., INC. (1.46)
SCOTT DERR PAINTING CO, LLC (0.30)
FARR FOUNDATION, INC. (1.39)
COX CONTRACTORS, INC. (0.65)
CURB PLANET INC. (0.00)
WEBBER BARRIER SERVICES, LLC. (0.76)
PROFESSIONAL TRAFFIC CONTROL, LLC (0.07)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.22)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.88)
HEMPHILL PILE DRIVING CO., A CORP. (0.01)
SITAR CONSTRUCTION, LLC (0.11)
TX DOWN UNDER CONSTRUCTION, LLC (0.01)
ENCINO LANDSCAPE, INC. (0.17)
ROY LEE WALKER (0.01)
SOUTHEAST GRINDING & GROOVING, LLC (0.11)
Contract #06123008
Totals52179225.210.0052256302.0899.9

page 1 | page 2 | page 3 | page 4