Monthly State Let Construction Report For Amarillo District As Of Jan 11, 2017 Page 1 Of 2

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyOCHILTREE ETC
HighwayUS 83 ETC
FromOKLAHOMA STATE LINE
ToSH 15
CSJ0030-01-032
Proj IDSTP 2016(152)
Work TypeSEALCOAT
 
223.2517967738.817746312.7597.2
Work Order01-29-16
Work Began07-18-16
Work Completed
Time Computed02-29-16
Contract Working Days94
Addl Days Granted0
Working Days Charged93
Percent Time Used98
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-01-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12153025
Totals7967738.81117699.127746312.7597.2

CountyOCHILTREE ETC
HighwayUS 83 ETC
FromSH 15
ToPEER STREET (PERRYTON)
CSJ0030-02-047
Proj IDNH 2017(260)
Work TypeSEALCOAT
 
313.26012438153.530.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-20-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days76
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LIPHAM ASPHALT AND PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-02-047
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11163003
Totals12438153.530.000.000.0

CountyLIPSCOMB
HighwayUS 83
FromOCHILTREE COUNTY LINE
ToHEMPHILL COUNTY LINE
CSJ0030-04-017
Proj IDSTP 2015(471)
Work TypeRESTORATION OF EXISTING ROADWAY
 
3.2422804932.542911824.1699.9
CountyHEMPHILL
HighwayUS 83
FromHORSE CREEK
ToUS 60
CSJ0030-05-063
Proj IDSTP 2015(471)
Work TypeRESTORATION
 
5.9954693999.684332888.6392.3
Work Order03-03-15
Work Began08-06-15
Work Completed
Time Computed07-01-15
Contract Working Days125
Addl Days Granted3
Working Days Charged121
Percent Time Used94
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-04-017
ALTUS TRAFFIC MANAGEMENT LLC (0.20)
BARRICADES UNLIMITED (0.70)
DUSTROL, INC. (4.07)
MARCOM"S MOWING SERVICE, LLC (0.29)
ODUM SERVICES, L.P. (5.33)
SCR CONSTRUCTION CO., INC. (0.63)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.09)
TEXAS ALTERNATIVE GRASSER, INC. (0.33)
VANCE BROTHERS, INC. (2.41)
Contract #01153003
Totals7498932.2214187.997244712.7996.6

CountyHEMPHILL
HighwayUS 60
FromUS 83/ US 60 INTERCHANGE
ToCANADIAN
CSJ0030-06-056
Proj IDNH 1502(077)
Work TypeREHAB EXISTING ROADWAY
 
6.37212716824.2911972750.9594.1
CountyHEMPHILL
HighwayUS 60
FromUS 83
ToLIPSCOMB COUNTY LINE
CSJ0170-01-032
Proj IDNH 1502(077)
Work TypeREHAD EXISTING ROADWAY
 
13.3006889749.106692620.3597.1
Work Order07-10-15
Work Began04-11-16
Work Completed
Time Computed05-01-16
Contract Working Days170
Addl Days Granted20
Working Days Charged167
Percent Time Used87
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0030-06-056
BARRICADES UNLIMITED (0.93)
HJC FARMS, INC. (5.33)
HUDSON, INC. (1.75)
INDUSTRIAL FABRICS, INC. (3.40)
PRIMATE CONSTRUCTION, INC. (0.05)
SAENZ TRANSPORT, LLC (0.00)
SILVER CREEK CONSTRUCTION, INC. (3.12)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.07)
TEXAS ALTERNATIVE GRASSER, INC. (0.06)
ROCK HARD TRUCKING LLC (0.00)
Contract #05153004
Totals19606573.39145879.4318665371.3095.1

CountyDALLAM ETC
HighwayUS 87 ETC
FromUS 54
ToLINCOLN STREET
CSJ0040-03-059
Proj IDNH 1502(569)
Work TypeUPGRADE TO STANDARDS NON-FREEWAY
 
4.35626321210.0015366308.5158.3
Work Order02-02-16
Work Began03-14-16
Work Completed
Time Computed03-03-16
Contract Working Days443
Addl Days Granted7
Working Days Charged122
Percent Time Used27
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0040-03-059
BARRICADES UNLIMITED (0.31)
A BROTHERS MILLING, LLC (1.02)
TLJ LINING CO. (0.09)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.38)
MCL CONTRACTING, LLC (0.02)
G AND G OPERATORS, LTD. (4.59)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.32)
J. LEE MILLIGAN, INC. (16.97)
PRIMATE CONSTRUCTION, INC. (0.71)
BREDA COMPANY, INC. (0.74)
KLP COMMERCIAL, LLC (4.23)
FARR FOUNDATION, INC. (0.83)
AR DANIEL CONSTRUCTION SERVICES, INC. (0.48)
SIGNAL SERVICES GROUP INC. (2.60)
ACTION CONSTRUCTORS (5.98)
SLATON BROTHERS, INC. (1.98)
Contract #08153216
Totals26321210.00606450.2415366308.5158.3

CountyHARTLEY
HighwayUS 87
FromDALHART
ToHARTLEY
CSJ0041-01-045
Proj IDNH 2015(298)
Work TypeREHAB EXISTING ROADWAY
 
12.0486272205.986188653.7998.6
CountyHARTLEY
HighwayUS 87
FromDALHART
ToHARTLEY
CSJ0041-01-046
Proj IDNH 2015(298)
Work TypeREHAB EXISITNG ROADWAY
 
12.0022901153.683628596.6599.9
Work Order01-02-15
Work Began07-28-15
Work Completed
Time Computed07-28-15
Contract Working Days120
Addl Days Granted0
Working Days Charged116
Percent Time Used96
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0041-01-045
BARRICADES UNLIMITED (1.62)
HJC FARMS, INC. (1.64)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.29)
TEXOP CONSTRUCTION (3.88)
J C DIAZ TRUCKING (3.00)
CF TRUCKING, LLC (1.28)
Contract #11143204
Totals9173359.666325.009817250.4499.9

CountyPOTTER
HighwayUS 60
FromON BUCHANAN FROM 11TH TO 6TH
ToON 6TH FROM FILLMORE TO PIERCE
CSJ0168-10-069
Proj IDSTP 2014(103)TE
Work TypeTRANSPORTION ENHANCEMENT
 
0.3632147565.300.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-05-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days95
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0168-10-069
QLVS, INC. DBA PHASE 3 ELECTRIC (9.34)
Contract #05163222
Totals2147565.300.000.000.0

CountyROBERTS ETC
HighwayUS 60 ETC
From.556 MI W OF RM 748
ToGRAY COUNTY LINE
CSJ0169-08-022
Proj IDSTP 2016(515)HESG
Work TypeCENTERLINE TEXTURING
 
227.625996579.09788116.4279.0
Work Order03-09-16
Work Began03-21-16
Work Completed
Time Computed04-08-16
Contract Working Days76
Addl Days Granted0
Working Days Charged75
Percent Time Used98
Contractor(s)
FLAT LINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0169-08-022
WEST TEXAS RUMBLE STRIP (11.08)
Contract #01163237
Totals996579.0912478.00788116.4279.0

CountyDEAF SMITH
HighwayUS 385
From.8 MILE SOUTH OF FM 1062
To1 MILE SOUTH OF OLDHAM COUNTY LINE
CSJ0226-04-025
Proj IDSTP 2016(680)
Work TypeRESTORATION
 
22.9088318208.262896873.2634.8
Work Order03-08-16
Work Began00-00-00
Work Completed
Time Computed03-08-16
Contract Working Days77
Addl Days Granted0
Working Days Charged61
Percent Time Used79
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0226-04-025
BARRICADES UNLIMITED (0.99)
DUSTROL, INC. (1.14)
HJC FARMS, INC. (0.72)
DIAMOND SURFACE, INC. (0.25)
HARDY TREES, INC. (0.43)
Contract #02163229
Totals8318208.260.002896873.2634.8

CountySHERMAN
HighwayUS 54
FromSTRATFORD CITY LIMITS
ToOKLAHOMA STATE LINE
CSJ0238-06-029
Proj IDNH 2016(682)
Work TypeOVERLAY
 
18.6317825684.437987677.1599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-08-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days57
Addl Days Granted0
Working Days Charged55
Percent Time Used96
Contractor(s)
HIGHWAY CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0238-06-029
BARRICADES UNLIMITED (1.19)
WOLFE CONSTRUCTION GROUP, INC. (0.27)
WEST TEXAS RUMBLE STRIP (0.10)
CUTTING EDGE MOWING SERVIES, LLC (0.00)
STAN"S ASPHALT & CONSTRUCTION (1.57)
TRIPLE F TRUCKING, LLC (3.37)
Contract #02163007
Totals7825684.430.007987677.1599.9

CountyPOTTER ETC
HighwayIH 40 ETC
FromHELIUM ROAD
ToEAST OF SL 335
CSJ0275-01-166
Proj IDNH 1502(372)
Work TypeRELOCATE ENTRANCE AND EXIT RAMPS
 
5.17926403959.2515143259.1657.3
Work Order10-06-15
Work Began01-25-16
Work Completed
Time Computed11-02-15
Contract Working Days560
Addl Days Granted12
Working Days Charged216
Percent Time Used37
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-166
ALAMO BROTHERS CONCRETE (4.85)
DUSTIN ALLEN, INC. (0.52)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.47)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.23)
WILLIS ELECTRIC CO., LP (10.58)
MCL CONTRACTING, LLC (0.16)
MICA CORPORATION (3.01)
L. A. FULLER & SONS CONSTRUCTION, LTD. (19.71)
SCOTT DERR PAINTING CO, LLC (0.16)
BREDA COMPANY, INC. (2.66)
BARRICADES UNLIMITED (0.95)
TRUMBLE CRANE & RIGGING (0.23)
A BROTHERS MILLING, LLC (0.23)
WOLFE CONSTRUCTION GROUP, INC. (0.04)
TRI-STATE OILFIELD SERVICES, INC. (0.02)
JOSH FRANKLIN DRILLING, LLC (0.04)
OSCAR ORDUNO, INC. (1.84)
MCL CONTRACTING, LLC (0.01)
ALAMO BROTHERS CONCRETE (0.20)
SLATON BROTHERS, INC. (3.58)
Contract #07153253
Totals26403959.25301686.8815143259.1657.3

CountyPOTTER
HighwayIH 40
FromAT SL335 (LAKESIDE)
To.
CSJ0275-01-168
Proj IDNH 1502(349)
Work TypeCONSTRUCT TURNAROUNDS
 
0.3402519584.252639205.2999.9
CountyRANDALL
HighwaySL 335
From0.13 MILES EAST OF GEORGIA ST.
To0.26 MILES WEST OF FM 1541
CSJ2635-02-028
Proj IDSTP 2013(605)
Work TypeCONVERT NON-FREEWAY TO FREEWAY
 
0.80817821897.2015500607.8586.4
Work Order07-31-15
Work Began08-10-15
Work Completed
Time Computed08-10-15
Contract Working Days460
Addl Days Granted0
Working Days Charged338
Percent Time Used73
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-168
TRUMBLE CRANE & RIGGING (0.21)
DUSTIN ALLEN, INC. (1.07)
L. A. FULLER & SONS CONSTRUCTION, LTD. (22.92)
WILLIS ELECTRIC CO., LP (1.80)
OSCAR ORDUNO, INC. (3.65)
BARRICADES UNLIMITED (0.65)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.67)
INDUS CONSTRUCTION, L.P. (1.34)
MCL CONTRACTING, LLC (0.13)
BREDA COMPANY, INC. (3.57)
ALAMO BROTHERS CONCRETE (0.42)
CINTEREX US, INC. (1.46)
WOLFE CONSTRUCTION GROUP, INC. (0.07)
A BROTHERS MILLING, LLC (0.64)
PENHALL COMPANY (0.09)
LLOYD D. NABORS DEMOLITION LLC (0.62)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00)
J. LEE MILLIGAN, INC. (0.55)
DISCOUNT FENCE COMPANY (0.10)
Contract #04153057
Totals20341481.45503309.3218139813.1488.7

CountyPOTTER
HighwayIH 40
From0.15 MILES WEST OF WASHINGTON ST
ToNELSON STREET
CSJ0275-01-177
Proj IDNH 1602(189)
Work TypeREHAB EXISTING ROADWAY
 
2.97736259776.702166319.425.9
Work Order09-26-16
Work Began11-01-16
Work Completed
Time Computed10-31-16
Contract Working Days332
Addl Days Granted0
Working Days Charged30
Percent Time Used9
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-177
BARRICADES UNLIMITED (1.47)
TRUMBLE CRANE & RIGGING (0.15)
HOWELL SAND CO. (1.54)
A BROTHERS MILLING, LLC (0.52)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.33)
BOWMAN ENGINEERING & CONSULTING, INC (2.70)
ER HAWKINS, LLC (1.81)
UNDER CONSTRUCTION INC. (0.31)
L. A. FULLER & SONS CONSTRUCTION, LTD. (12.18)
W. W. FOUNDATION DRILLING, LTD. (1.81)
HJC FARMS, INC. (2.16)
WILLIS ELECTRIC CO., LP (3.73)
OSCAR ORDUNO, INC. (1.49)
SOUTH TEXAS PAINTING COMPANY (0.59)
MICA CORPORATION (0.72)
Contract #06163003
Totals36259776.701879373.272166319.425.9

CountyGRAY
HighwayIH 40
FromALANREED
ToDONLEY COUNTY LINE
CSJ0275-11-077
Proj IDNH 1502(079)
Work TypeOVERLAY AND MINOR BRIDGE MAINTENANC
 
9.5713565812.593454996.8996.8
Work Order06-15-15
Work Began08-01-16
Work Completed
Time Computed09-01-15
Contract Working Days76
Addl Days Granted0
Working Days Charged69
Percent Time Used90
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-11-077
BARRICADES UNLIMITED (2.13)
HJC FARMS, INC. (1.19)
O. TREVINO CONSTRUCTION, LLC (5.61)
TEX OP CONSTRUCTION, LP (1.79)
WEST TEXAS RUMBLE STRIP (0.11)
Contract #05153223
Totals3565812.590.003454996.8996.8

CountyHANSFORD
HighwaySH 15
FromSH 136 IN GURVER
ToSH 207 IN SPEARMAN
CSJ0308-02-029
Proj IDSTP 1602(139)
Work TypeRESTORATION OF EXISTING ROADWAY
 
19.9009135715.4253625.000.5
Work Order07-28-16
Work Began00-00-00
Work Completed
Time Computed08-26-16
Contract Working Days210
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0308-02-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05163030
Totals9135715.420.0053625.000.5

CountyLIPSCOMB
HighwaySH 15
FromFM 1455
ToOKLAHOMA STATE LINE
CSJ0355-01-048
Proj IDSTP 1602(191)
Work TypeOVERLAY
 
12.3624980635.650.000.0
CountyLIPSCOMB
HighwaySH 15
FromOCHILTREE COUNTY LINE
To1000' EAST OF COUNTY ROAD 4
CSJ0355-02-031
Proj IDSTP 1602(191)
Work TypeOVERLAY
 
3.118986876.400.000.0
CountyLIPSCOMB
HighwaySH 23
FromFM 377
To11.05 MILES NORTH OF US 83
CSJ1337-01-023
Proj IDSTP 1602(191)
Work TypeOVERLAY
 
10.0632183107.750.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-05-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days77
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0355-01-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06163023
Totals8150619.800.000.000.0

CountyCARSON
HighwaySH 207
FromFM 293
ToHUTCHINSON COUNTY LINE
CSJ0356-02-043
Proj IDSTP 2014(866)
Work TypeRESTORATION OF EXISTING ROADWAY
 
19.1028607481.828651167.5199.9
Work Order09-30-14
Work Began10-22-14
Work Completed
Time Computed10-16-14
Contract Working Days110
Addl Days Granted9
Working Days Charged145
Percent Time Used121
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0356-02-043
BARRICADES UNLIMITED (1.16)
E. DIAZ TRUCKING (4.32)
DUSTROL, INC. (1.37)
RICE ENVIRONMENTAL SERVICES (1.81)
TEXAS ALTERNATIVE GRASSER, INC. (0.77)
WEST TEXAS RUMBLE STRIP (0.32)
Contract #07143211
Totals8607481.8222866.508651167.5199.9

CountyGRAY
HighwaySH 152
FromUS 60
ToWHEELER COUNTY LINE
CSJ0397-01-043
Proj IDSTP 2015(472)
Work TypeOVERLAY
 
17.7356779225.716785785.7099.9
Work Order02-11-15
Work Began09-22-15
Work Completed
Time Computed06-15-15
Contract Working Days52
Addl Days Granted0
Working Days Charged79
Percent Time Used151
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0397-01-043
BARRICADES UNLIMITED (1.88)
DUSTROL, INC. (0.41)
HJC FARMS, INC. (4.71)
Contract #01153208
Totals6779225.717644.006785785.7099.9

CountyROBERTS
HighwaySH 70
FromNORTH CANADIAN RIVER BRIDGE
ToOCHILTREE COUNTY LINE
CSJ0490-04-037
Proj IDSTP 2014(579)
Work TypeREHABILITATE EXISTING ROADWAY
 
5.8485139086.584999710.1799.4
Work Order06-18-14
Work Began12-10-14
Work Completed
Time Computed09-02-14
Contract Working Days197
Addl Days Granted27
Working Days Charged321
Percent Time Used143
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0490-04-037
BARRICADES UNLIMITED (0.99)
HJC FARMS, INC. (3.77)
HUDSON, INC. (0.81)
TEXAS ALTERNATIVE GRASSER, INC. (0.43)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.84)
WEST TEXAS RUMBLE STRIP (0.08)
W.S. CONSTRUCTION COMPANY (5.84)
E. DIAZ TRUCKING (2.85)
Contract #04143003
Totals5139086.5822172.004999710.1799.4

CountyMOORE
HighwaySH 152
FromDUMAS CITY LIMITS
ToHUTCHINSON COUNTY LINE
CSJ0557-01-028
Proj IDSTP 2016(683)
Work TypeRESTORATION
 
47.26315561610.539100993.7358.4
Work Order05-24-16
Work Began07-06-16
Work Completed
Time Computed06-23-16
Contract Working Days130
Addl Days Granted20
Working Days Charged87
Percent Time Used58
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0557-01-028
BARRICADES UNLIMITED (0.84)
DUSTROL, INC. (2.04)
W.S. CONSTRUCTION COMPANY (1.58)
CF TRUCKING, LLC (1.46)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.11)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.15)
HJC FARMS, INC. (0.21)
Contract #02163003
Totals15561610.5357368.589100993.7358.4